A private house takes about a hundred weeks from the first visit to handover. This is where the time goes.

  1. 1

    Survey and brief

    We measure the site, read the regulations and write the brief with you.

    4 weeks
  2. 2

    Concept design

    Two or three massing options, tested in the model and costed in outline.

    8 weeks
  3. 3

    Planning

    We prepare and submit the application, and answer the authority's questions.

    12 weeks
  4. 4

    Technical design

    Every junction drawn, every product specified, engineers coordinated in one model.

    14 weeks
  5. 5

    Tender

    Contractors price the same complete set. We compare their offers line by line.

    6 weeks
  6. 6

    Construction

    Weekly site meetings, drawings kept current, payments certified against work done.

    52 weeks
  7. 7

    Handover

    Snag list closed, as-built model and maintenance manual delivered.

    4 weeks

Larger buildings follow the same seven stages over a longer programme. We set out the dates for yours after the first site visit: tell us about your site.