A private house takes about a hundred weeks from the first visit to handover. This is where the time goes.
-
1
4 weeks
Survey and brief
We measure the site, read the regulations and write the brief with you.
-
2
8 weeks
Concept design
Two or three massing options, tested in the model and costed in outline.
-
3
12 weeks
Planning
We prepare and submit the application, and answer the authority's questions.
-
4
14 weeks
Technical design
Every junction drawn, every product specified, engineers coordinated in one model.
-
5
6 weeks
Tender
Contractors price the same complete set. We compare their offers line by line.
-
6
52 weeks
Construction
Weekly site meetings, drawings kept current, payments certified against work done.
-
7
4 weeks
Handover
Snag list closed, as-built model and maintenance manual delivered.
Larger buildings follow the same seven stages over a longer programme. We set out the dates for yours after the first site visit: tell us about your site.